Six questions before you trust the program's status.

Ask for the evidence behind each answer, who owns the next action and which agency official can decide. The checklist supports a review; it does not replace your agency's requirements or acceptance.

Six program questions, with evidence for eachIllustrative isometric program health review card with six numbered review questions and a stack of supporting records. The illustration represents a review, not an approval or audit opinion.123456Six questionsEvidence for each
Six questions. Evidence for each. Agency decisions recorded.

01

Is there one integrated schedule that meets GAO's ten schedule practices, and one decision log?

Examine: The current integrated schedule, its approved baseline, the assessment against the GAO Schedule Assessment Guide, and the decision log. Check that dependencies and staffing gates are represented and that approved changes can be traced.

Agency role: The program executive or sponsor approves the baseline within the agency's authority. The government program manager reviews the schedule and the decisions needed.

02

Does every variance in the last report have an owner and a decision?

Examine: The last program report, the underlying measure definitions and the corrective action record. Each variance should show its cause, effect, action owner and the decision taken or still required. Check whether completed actions were tested for effectiveness.

Agency role: The program executive or delegated review body takes program decisions. Only the contracting officer approves changes to contract scope or terms.

03

Does every position have a risk designation, and was the start date planned from it?

Examine: The staffing plan, agency position designations, labor category requirements and the status of vetting and access gates. Confirm that sourcing began from the position's risk and applicable national-security sensitivity requirements and that planned dates reflect the agency's decisions rather than an assumed clearance timeline.

Agency role: The agency designates the position. The personnel security office confirms the applicable vetting requirements and determinations.

04

Is signed consent on file for every person named in the proposal, and is availability current?

Examine: The named-person register, signed consent records, availability confirmations and key personnel approvals. Check that a proposed person's withdrawal or a material availability change was escalated and that a backup is not being treated as an approved substitute.

Agency role: The contracting officer receives material personnel changes and approves key personnel or substitutions as the contract requires. Consent records remain in approved channels.

05

When someone leaves, is access closed on your agency's clock?

Examine: The separation or reassignment record, required notifications, account revocation evidence and credential return. Check logical and physical access separately, including shared credentials and any pending vetting actions. A departure date alone does not prove closure.

Agency role: The responsible security and access officials verify closure. The COR confirms receipt of the records required by the contract.

06

Could another team take the program over next quarter without a break in service?

Examine: The current transition plan, handover register, receiving-team walkthroughs and readiness test results. Each person, process, system, record, credential, asset and decision right needs an owner, a receiving owner and a date. Check the joint property and data inventory, receiving-team demonstrations, rollback arrangements, incident ownership and stabilization measures. Keep failed tests and unresolved risks visible.

Agency role: Designated agency officials decide readiness, and the COR acts within the written delegation. The contracting officer approves contractual transition terms and any required changes.